Staff shortage hits MTR's project to bore through mountain for Sha Tin-Central link
Drilling through mountain provides MTR with its latest challenge, as tunnel work turns off staff and ground conditions prove uncertain
Boring through the mountain below Lion Rock is shaping up as the next challenge for the MTR in the construction of the delayed Sha Tin-Central link, with a labour shortage and uncertainty about ground conditions.
"No one has done any construction through the mountain since the Lion Rock Tunnel opened decades ago, so there could be many uncertainties in the process," he said.
"If you went hiking on the mountain, you would see there's a lot of erosion. We don't know if that's also the case in its middle."
The line is estimated to be 11 months behind schedule because of the excavation of ancient relics at the To Kwa Wan station site.
The first phase, from Tai Wai to Hung Hom, is scheduled for completion by 2018.
The second phase, from Hung Hom to Admiralty, is scheduled to open in 2020.